A Certificate of Final Inspection (CFI) or an Occupancy Permits (OP) must also be submitted along with any amendments or variations to a building permit.
Section 80 notification
A Section 80 is required to be submitted to Council within 7 days of a Private Building Surveyor (PBS) accepting an appointment to issue a building permit for building works. Please ensure you include a detailed description of the works.
Lodge your Section 80 online
Section 30 documentation
The Relevant Building Surveyor (RBS) must within 7 days lodge any building permit issued including a copy of that building permit, and other documents lodged with the application for that permit.
For new building permits, lodge your Section 30 documents onlineOpens in new tab.
For staged building permits, any documents relating to subsequent stages will still need to be submitted via email to building@melbourne.vic.gov.au.
Lodge your Section 30 documents online
Certificate of Final Inspection (CFI) and Occupancy Permits (OP)
Depending on the works, the Relevant Building Surveyor (RBS) may issue a Certificate of Final Inspection (CFI) or an Occupancy Permit (OP). It is an offence under the Building Act 1993 to occupy a building prior to receiving an OP.
Lodge your Certificate of Final Inspection (CFI) or Occupancy Permit (OP) online
Building Permits Amendments (PBA), Building Permits Variations (BPV) and Other Building permits (BPO)
Any amendments or variations to a building permit (supporting Building Permit documentation) can now also be lodged online. Lodge your Building Permit Amendments, Variations and Other Building permits onlineOpens in new tab.