Flinders Street long-term closure | September 2019 to August 2024 | Flinders Street at Degraves Street. Full eastbound closure between Elizabeth Street and Swanston Street. Visit Big Build for more information. | Metro Tunnel Project |
Elizabeth Street | February 2023 to July 2024 | Sections of the northbound lanes on Elizabeth Street between Lonsdale and Victoria Streets will be closed. Daytime and night time works. Visit Greater Western Water for more information. | Sewer main renewal |
La Trobe Street long-term closure | September 2023 for up to 12 months | La Trobe Street full eastbound closure between Elizabeth and Swanston streets. Visit Big Build for more information. | Metro Tunnel Project |
Franklin Street, Queen and Peel streets | 3 October 2023 to April 2024 | Franklin Street, Queen Street and Peel Street. There will be some temporary traffic and parking impacts. Local traffic and pedestrian access will be maintained at all times with traffic control in place to safely guide vehicles, cyclists and pedestrians. | Power utility works |
A'Beckett Street long-term closure | June 2017 to end 2024 | A'Beckett Street is closed between Swanston Street and Stewart Street. Long-term closure. Visit Big Build for more information. | Metro Tunnel Project |
Franklin Street long-term closure | 16 January to mid-2024 | Full and partial road closures on Franklin Street between Swanston Street and Elizabeth Street. 24 hours. Monday to Saturday. Visit Big Build for more information. | Metro Tunnel Project |
Grattan Street, Parkville long-term closure | January 2024 to mid 2024 | Grattan Street will be closed to vehicles and cyclists between Royal Parade and Leicester Street. Visit Big Build for more information. | Metro Tunnel Project |
Victoria Street | 28 January to 30 June 2024 | Full westbound road closure between Peel Street and Capel Street. 7pm to 6am Weeknights, Saturdays & Sundays. | Victoria Street water works |
Macaulay Road and Barnett Street, Kensington | 7 March to 30 April 2024 | Macaulay Road partial southern footpath closure and partial westbound carriageway closure between Eastwood Street and Bent Street. Barnett St full north and southbound carriageway closure between Macaulay Road and Robertson St. Monday till Saturday, Night works: 10pm - 4am (27/02/2024 - 07/03/2024, 14/03/2024 - 14/04/2024).
Macaulay Road partial eastbound carriageway and full northern footpath closure between Bent St and Albermarle St. 9am to 3pm weekdays, 8am to 3pm Sat (30/03/2024 - 30/04/2024). | Utility works |
Exhibition Street | 4 March to 17 May 2024 | Full and partial closures between Little Bourke Street and Lonsdale Street. Visit Exhibition Street Theatre Precinct streetscape improvements for more information.
| City of Melbourne Project |
Grattan Street, Carlton | 26 February to 7 June 2024 | Partial carriageway closures and intermittent full road closures. Visit New bike lanes for more information.
| Grattan Street Bike Lane Upgrade |
Little La Trobe Street long-term closure | Tuesday 19 March until the end of September 2024 | Road closure of Little La Trobe Street between Elizabeth and Swanston streets. 24 hours. During the works, motorist access to and from Little La Trobe Street and Literature Lane will be maintained via Elizabeth Street. Local vehicle access to businesses and residential buildings will be maintained at all times under traffic control. Pedestrian access will be maintained at all times. Visit Big Build for more information. | Metro Tunnel Project |
Stubbs Street, Kensington | 12 March to 2 June 2024 | Stubbs Street full carriageway closure with shuttle flow between Parsons Street and Smith Street, Kensington. 7am to 5pm. | Power utility works |
Chelmsford Street | 30 March to 30 April 2024 | Chelmsford Street full carriageway closure between Eastwood Street and Elizabeth Street. 9am to 4.30pm weekdays, 8am to 3pm Sat. | Utility works |
Leicester Street | 1 April to 30 April 2024 | Leicester Street full southbound carriageway closure between Queensberry Street and Pelham Street Carlton. Weekdays 9.30am to 3.30pm, Saturday 8am to 3pm. | Utility works |
Dryburgh St, Brougham St, and Abbotsford St, North Melbourne | 17 April, 24 April and 1 May 2024 | Full westbound carriageway Closure on Dryburgh St. Full carriageway closure on Brougham St. Full northern carriageway closure on Abbotsford Street. Multiple Wednesdays. 7am to 7pm. | Utility works |
Kavanagh Street, Southbank | 28 February to 8 May 2024 | Full Southbound Carriageway Closure on Kavanagh Street between Southbank Boulevard and Power Street. Weekdays 7am to 7pm and Saturdays 8am to 3pm. | Utility works |
Drummond Street | 17 April to 31 May 2024 | Drummond Street full southbound carriageway closure between Faraday Street and Elgin Street. 7am to 4pm. | Streetscape improvement works |
Turner Street, Port Melbourne | 6 May to to 10 May 2024 | Turner Street full westbound carriageway closure between Salmon Street and Douglas Street. 7am to 5pm. | Building and construction works |
Williams Street and Flinders Lane | 13 April to 5 May 2024 | Williams Street full southbound carriageway and eastern footpath closure between Flinders Lane and Collins Street, Flinders Lane full eastbound carriageway and northern footpath closure between Market Street and William Street. Saturday 8am to 3pm, Sunday 10am to 5pm. | Building and construction works |
Dodds Street | 1 to 3 May 2024 | Dodds Street full western footpath closure and full carriageway closure between Miles Street and Grant Street. 7am to 7pm. | Building and construction works |
Flinders Lane | Saturday 4 May and 18 May 2024 | Flinders Lane full carriageway closure between Swanston Street and Elizabeth Street. 8am to 3pm. | Building and construction works |